Forest City Tower
Wadi Al Safa 3 · Al Helal Al Zahaby Real Estate Development L.L.C · Selling off-plan
Starting price · developer—not published by the developer
Sold, median · DLDAED1.31MDLD · 74 sales, 12 months
Planned end · DLDApr 2027DLD planned end
Built · DLD register70%DLD register, Nov 2026
From the developer
The developer’s prices are not available here yet. An advisor can send the price list, payment plan and availability.
From DLD’s records
sales to 9 Nov 2026- Sales, 12 months
- 74 · 100% off-plan
- Median sale
- AED 1,314,651
- Average per sq ft
- AED 1,218
- First sale
- 20 Dec 2024
- Construction
- 70% built, planned end Apr 2027 (register as of Nov 2026)
- Homes registered
- 253
Still off-plan: its sales up to 9 Nov 2026 are off-plan, so it has not handed over. DLD's register (as of November 2026) shows 70% complete and a planned end of 9 Apr 2027.
Registered sales, cleaned as LEA cleans them. DLD project number 3330. Full sales record by bedroom
Questions about Forest City Tower
What have homes in Forest City Tower sold for?
Over the twelve months to 9 Nov 2026, 74 sales were registered with the Dubai Land Department at a median of AED 1,314,651 and an average of AED 1,218 per square foot.
When is Forest City Tower handing over?
DLD's project register gives a planned end of Apr 2027 (as DLD last published it, Nov 2026).